info@life-f4f.gr    +30 2810 361610

Work Modules – Deliverables

LIST OF ALL ACTIONS

A. Project actions

ACTION B.1: Development of the Source Separated Food Waste Collection System
B. 1.1. From the kitchen and the table to the F4F unit – evaluating source separation systems, selecting hotels, designing optimum collection route.
B.1.2. Cost estimation methodology for the food wastes collection system.

ACTION B.2: Developing the F4F Pilot Unit
B2.1. Acquire the needed licenses for buildings works.
B2.2. Construct the required units.
B2.3. The turners, the floor heating system and various other equipment.

ACTION B.3: Initiating, Operating and Optimising the F4F System
B.3.1. Tendering the waste collection and hand sorting service.
B3.2. Initial operational period.
B3.3. 1st full scale operational period.
B3.4. 2nd and optimum operational period.

ACTION B.4: Evaluating the Produced Feed for Pigs and Poultry Husbandry
B4.1. Analysis of produced feed
B4.2. Animals’ feeding trials
B4.3. Additions and alterations in the pilot unit

ACTION B.5: Evaluating the Produced Feed as Pet Food
B5.1. Analysis of the feed
B5.2. Production of complete diets for dogs and cats with varying amounts of feed
B5.3. Additions and alterations in the pilot unit

ACTION B.6: Products’ Customer Survey, Technical Scale Up, Economical and Environmental Evaluation and Replicability and Transferability of the F4F Process
B6.1. Customer survey
B6.2. Economical evaluation and business plan
B.6.3: Environmental evaluation
B6.4. Technical scale up, design and construction manuals
B6.5. Operational manuals

ACTION B.7: Completing, Incorporating and Evaluating the F4F Process as Part of the EU’s Wastes Strategy and other Union Policies
B7.1. Alternative use of the produced feed.
B7.2. F4F process in relation to the wastes strategy
B7.3. The F4F in the resources efficiency roadmap and policies
B7.4. Securing funding for operating a F4F unit

B. Project deliverables

Deliverable Name Action B.1. Foreseen date
List of targeted and selected hotels and their operational characteristics 10/2016
Selected hotels for the needs of the F4F project cooperation agreements signed 12/2016
Selected hotels source separation system qualitatively & quantitative survey 11/2017
Short listed and selected hotels optimum collection routes 12/2017
Food wastes collection cost estimation system 12/2017

 

Deliverable Name Action B.2. Foreseen date
All licenses for the development of the pilot unit 02/2017
The building for sorting and grinding and the solar drying halls 05/2017
The full operational solar drying pilot unit 07/2017
The solar drying turners and various other equipment 06/2017

 

Deliverable Name Action B.3. Foreseen date
Data, results and feed produced, during the initiating operational period 01/2018
Data, results and feed produced, during the first full scale operational period 01/2019
Optimum operational mode 12/2019
Data, results and feed produced, during the optimum operational period 01/2020
Data, results and biodiesel produced during project 01/2020

 

Deliverable Name Action B.4. Foreseen date
Complete chemical analysis of the produced feed, through the pigs and poultry husbandry perspective 10/2018
Indications of shortcomings of the production process, in relation to the product’s use for pigs and poultry husbandry, and suggestion for improvements. 12/2018
Economic evaluation of the produced feed, regarding pigs and poultry husbandry 12/2018
Complete evaluation of the produced feed for pigs and poultry husbandry 12/2019

 

Deliverable Name Action B.5. Foreseen date
Complete chemical analysis of the produced feed, through the pet food industry perspective 10/2018
Complete evaluation of the produced feed for pets 12/2018
Economic evaluation of the produced feed, regarding pet food utilisation 12/2018
Indicators of shortcomings of the production process, in relation to the product’s use for pet food, and suggestion for improvements 12/2019

 

Deliverable Name Action B.6. Foreseen date
Customer survey regarding pet food (industry & owners) 12/2018
Customer survey regarding pigs and poultry (farmers & consumers) 03/2019
Technical manuals and designs of a full scale unit 08/2019
Deliverable Name Action B.6. Foreseen date
Operational manuals of a full scale unit 12/2019
LCA and environmental evaluation 08/2019
Business plan of full scale unit 08/2019

 

Deliverable Name Action B.7. Foreseen date
Reports and suggestion regarding the role of F4F in the wastes management strategy and how it should be implemented as part of zero wastes scheme 08/2019
Reports and suggestions regarding the incorporation of the F4F process in the resources efficiency road map and relevant required improvements in the legislation 10/2019
Documents regarding the process towards funding the F4F unit through wastes’ management municipal taxation 11/2019
Data and complete evaluations regarding alternative uses of the F4F product 12/2019

 

Deliverable Name Action C.1. Foreseen date
First evaluation of performance indicators 08/2017
Assessment of the initial situation 09/2017
Impacts of the project if a full scale unit will be developed 12/2018
Qualitatively and quantitatively verification of the impact of the project actions during realisation 12/2018
S-LCA completed 02/2018
Mid-term evaluation of performance indicators 01/2019
Final evaluation of performance indicators 02/2020

 

Deliverable Name Action D.1. Foreseen date
Website and social media accounts 12/2016
Notice boards 08/2017
Leaflet and newsletter for the benefits and need of source separation in households, aiming for the general public 12/2018
General public leaflet 12/2018
Replicability and transferability activities report 12/2019
Networking report 12/2019
Report about dissemination activities towards private entities 12/2019
Open day events 10/2019
International conference 10/2019
Publication of academic papers 02/2020
Layman’s report 02/2020

 

Deliverable Name Action E.1. Foreseen date
1st progress report 08/2017
Mid-term report 01/2019
Final report 05/2020

 

C. Monitoring of the impact of the project actions (obligatory)

ACTION C.1: Monitoring of the impact of the project actions
C.1.1. Impact of the projects’ actions (excluding socio-economic)
C.1.2. Impact of the full scale realisation of the process (excluding socio-economic)
C.1.3.: Assessment of the project’s socio-economic impact

 

D. Public awareness and dissemination of results (obligatory)

ACTION D.1: Communication and dissemination actions
D1.1. Dissemination activities towards the general public.
D1.2. Dissemination activities toward professionals related with the F4F process
D1.3. Dissemination activities towards the academia and consultants
D.1.4: Layman’s report and notice boards
D.1.5. Networking
D.1.6. Dissemination activities towards private entities

 

E. Project management

ACTION E.1: Project management and monitoring of the project progress
E.1.1: Reporting to the EC
E.1.2: Use of external experts for evaluating progress
E.1.3.: Auditing
E.1.4. After LIFE+ communication plan