1.     Approved Deliverables Tables

 

Deliverable Name Action B1 Foreseen date Actual date

Amend. No2

List of targeted and selected hotels and their operational characteristics – Deliverable B1.1 10/2016 11/2016
Selected hotels for the needs of the F4F project cooperation agreements signed – Agapi Beach_Hotel_Contract Apollonia_Hotel_contract ARMY_contract ATLANTIS_hotel_contract Candia Maris_Hotel_contract CRETA MARIS_hotel_contract GALAXY_hotel_contract OLIVE GREEN_hotel_contract Santa Marina_Hotel_contract Siganos_hotel_contract XALKIADAKIS_SM_contract 12/2016 04/2017
Selected hotels source separation system qualitatively & quantitative survey – Deliverable B1.3 11/2017 11/2017
Short listed and selected hotels optimum collection routes – Deliverable B1.4 12/2017 05/2018
Food wastes collection cost estimation system – Deliverable B1.5 12/2017 05/2018

 

Deliverable Name Action B2 Foreseen date Actual date

Amend. No2

All licenses for the development of the pilot unit – Deliverable B2.1 02/2017 07/2017
The building for sorting and grinding and the solar drying halls – Deliverable B2.2 05/2017 06/2018
The full operational solar drying pilot unit – VIDEO 07/2017 06/2018
The solar drying turners and various other equipment – Deliverable B2.4 06/2017 06/2018

 

Deliverable Name Action B3 Foreseen date Actual date

Amend. No2

Data, results and feed produced, during the initiating operational period – Deliverable B3.1 01/2018 01/2019
Data, results and feed produced, during the first full scale operational period – Deliverable B3.2 01/2019 01/2020
Optimum operational mode 12/2019 12/2020
Data, results and feed produced, during the optimum operational period – Deliverable B3.4 01/2020 01/2021
Data, results and biodiesel produced during project – Deliverable B3.5 01/2020 01/2021

 

Deliverable Name Action B4 Foreseen date Actual date

Amend. No2

Complete chemical analysis of the produced feed, through the pigs and poultry husbandry perspective 10/2018 10/2019
Indications of shortcomings of the production process, in relation to the product’s use for pigs and poultry husbandry, and suggestion for improvements. 12/2018 12/2019
Economic evaluation of the produced feed, regarding pigs and poultry husbandry 12/2018 12/2019
Complete evaluation of the produced feed for pigs and poultry husbandry 12/2019 12/2020

 

Deliverable Name Action B5 Foreseen date Actual date

Amend. No2

Complete chemical analysis of the produced feed, through the pet food industry perspective – Deliverable B5.1 10/2018 10/2019
Complete evaluation of the produced feed for pets – Deliverable B5.2 12/2018 12/2019
Economic evaluation of the produced feed, regarding pet food utilisation – Deliverable B5.3 12/2018 12/2019
Indicators of shortcomings of the production process, in relation to the product’s use for pet food, and suggestion for improvements 12/2019 12/2020

 

Deliverable Name Action B6 Foreseen date Actual date

Amend. No2

Customer survey regarding pet food (industry & owners) 12/2018 12/2019
Customer survey regarding pigs and poultry (farmers & consumers) 03/2019 03/2020
Technical manuals and designs of a full scale unit 08/2019 08/2020
Operational manuals of a full scale unit 12/2019 12/2020
LCA and environmental evaluation – Deliverable B6.5 08/2019 08/2020
Business plan of full scale unit 08/2019 08/2020

 

Deliverable Name Action B7 Foreseen date Actual date

Amend. No2

Reports and suggestion regarding the role of F4F in the wastes management strategy and how it should be implemented as part of zero wastes scheme 08/2019 08/2020
Reports and suggestions regarding the incorporation of the F4F process in the resources efficiency road map and relevant required improvements in the legislation 10/2019 10/2020
Documents regarding the process towards funding the F4F unit through wastes’ management municipal taxation 11/2019 11/2020
Data and complete evaluations regarding alternative uses of the F4F product 12/2019 12/2020

 

Deliverable Name Action C1 Foreseen date Actual date

Amend. No2

First evaluation of performance indicators – Deliverable C1.1 08/2017 01/2019
Assessment of the initial situation – Deliverable C1.2 09/2017 01/2019
Impacts of the project if a full scale unit will be developed 12/2018 12/2019
Qualitatively and quantitatively verification of the impact of the project actions during realisation 12/2018 12/2019
S-LCA completed 02/2018 02/2021
Mid-term evaluation of performance indicators – Deliverable C1.6 01/2019 01/2020
Final evaluation of performance indicators 02/2020 02/2021

 

Deliverable Name Action D1 Foreseen date Actual date

Amend. No2

Website and social media accounts 12/2016 01/2017
Notice boards – Deliverable D1.2 08/2017 04/2018
Leaflet and newsletter for the benefits and need of source separation in households, aiming for the general public 12/2018 12/2019
General public leaflet – Deliverable D1.4_EN 12/2018 12/2019
Replicability and transferability activities report 12/2019 12/2020
Networking report 12/2019 12/2020
Report about dissemination activities towards private entities 12/2019 12/2020
Open day events 10/2019 02/2021
International conference 10/2019 02/2021
Publication of academic papers 02/2020 02/2021
Layman’s report 02/2020 02/2021

 

Deliverable Name Action E1 Foreseen date Actual date

Amend. No2

1st progress report 08/2017 09/2017
Mid-term report 01/2019 01/2019
2nd progress report 04/2020
Final report 05/2020 05/2021