Deliverable Name Action B.1. | Foreseen date |
List of targeted and selected hotels and their operational characteristics | 10/2016 |
Selected hotels for the needs of the F4F project cooperation agreements signed | 12/2016 |
Selected hotels source separation system qualitatively & quantitative survey | 11/2017 |
Short listed and selected hotels optimum collection routes | 12/2017 |
Food wastes collection cost estimation system | 12/2017 |
Deliverable Name Action B.2. | Foreseen date |
All licenses for the development of the pilot unit | 02/2017 |
The building for sorting and grinding and the solar drying halls | 05/2017 |
The full operational solar drying pilot unit | 07/2017 |
The solar drying turners and various other equipment | 06/2017 |
Deliverable Name Action B.3. | Foreseen date |
Data, results and feed produced, during the initiating operational period | 01/2018 |
Data, results and feed produced, during the first full scale operational period | 01/2019 |
Optimum operational mode | 12/2019 |
Data, results and feed produced, during the optimum operational period | 01/2020 |
Data, results and biodiesel produced during project | 01/2020 |
Deliverable Name Action B.4. | Foreseen date |
Complete chemical analysis of the produced feed, through the pigs and poultry husbandry perspective | 10/2018 |
Indications of shortcomings of the production process, in relation to the product’s use for pigs and poultry husbandry, and suggestion for improvements. | 12/2018 |
Economic evaluation of the produced feed, regarding pigs and poultry husbandry | 12/2018 |
Complete evaluation of the produced feed for pigs and poultry husbandry | 12/2019 |
Deliverable Name Action B.5. | Foreseen date |
Complete chemical analysis of the produced feed, through the pet food industry perspective | 10/2018 |
Complete evaluation of the produced feed for pets | 12/2018 |
Economic evaluation of the produced feed, regarding pet food utilisation | 12/2018 |
Indicators of shortcomings of the production process, in relation to the product’s use for pet food, and suggestion for improvements | 12/2019 |
Deliverable Name Action B.6. | Foreseen date |
Customer survey regarding pet food (industry & owners) | 12/2018 |
Customer survey regarding pigs and poultry (farmers & consumers) | 03/2019 |
Technical manuals and designs of a full scale unit | 08/2019 |
Deliverable Name Action B.6. | Foreseen date |
Operational manuals of a full scale unit | 12/2019 |
LCA and environmental evaluation | 08/2019 |
Business plan of full scale unit | 08/2019 |
Deliverable Name Action B.7. | Foreseen date |
Reports and suggestion regarding the role of F4F in the wastes management strategy and how it should be implemented as part of zero wastes scheme | 08/2019 |
Reports and suggestions regarding the incorporation of the F4F process in the resources efficiency road map and relevant required improvements in the legislation | 10/2019 |
Documents regarding the process towards funding the F4F unit through wastes’ management municipal taxation | 11/2019 |
Data and complete evaluations regarding alternative uses of the F4F product | 12/2019 |
Deliverable Name Action C.1. | Foreseen date |
First evaluation of performance indicators | 08/2017 |
Assessment of the initial situation | 09/2017 |
Impacts of the project if a full scale unit will be developed | 12/2018 |
Qualitatively and quantitatively verification of the impact of the project actions during realisation | 12/2018 |
S-LCA completed | 02/2018 |
Mid-term evaluation of performance indicators | 01/2019 |
Final evaluation of performance indicators | 02/2020 |
Deliverable Name Action D.1. | Foreseen date |
Website and social media accounts | 12/2016 |
Notice boards | 08/2017 |
Leaflet and newsletter for the benefits and need of source separation in households, aiming for the general public | 12/2018 |
General public leaflet | 12/2018 |
Replicability and transferability activities report | 12/2019 |
Networking report | 12/2019 |
Report about dissemination activities towards private entities | 12/2019 |
Open day events | 10/2019 |
International conference | 10/2019 |
Publication of academic papers | 02/2020 |
Layman’s report | 02/2020 |
Deliverable Name Action E.1. | Foreseen date |
1st progress report | 08/2017 |
Mid-term report | 01/2019 |
Final report | 05/2020 |